· Not an official government website

BatasKo

Ang Batas, Sa Simpleng Salita — your rights, finally explained.

Article 1724

RA 386 · Civil Code of the PhilippinesKey provision

ELI5— what this means for you

The contractor who undertakes to build a structure or any other work for a stipulated price, in conformity with plans and specifications agreed upon with the land-owner, can neither withdraw from the contract nor demand...

Official text — RA 386

The contractor who undertakes to build a structure or any other work for a stipulated price, in conformity with plans and specifications agreed upon with the land-owner, can neither withdraw from the contract nor demand an increase in the price on account of the higher cost of labor or materials, save when there has been a change in the plans and specifications, provided:

(1) Such change has been authorized by the proprietor in writing; and

(2) The additional price to be paid to the contractor has been determined in writing by both parties. (1593a)

Source: lawphil.net (RA 386 as amended)

Related

RELATED RIGHTS

Legal disclaimer: BatasKo provides general legal information, not legal advice. For advice on contracts, property rights, obligations, or civil damages, consult a licensed Filipino lawyer or the Public Attorney's Office (PAO) at pao.gov.ph.