Article 1722
ELI5— what this means for you
If the work cannot be completed on account of a defect in the material furnished by the employer, or because of orders from the employer, without any fault on the part of the contractor, the latter has a right to an...
Official text — RA 386
If the work cannot be completed on account of a defect in the material furnished by the employer, or because of orders from the employer, without any fault on the part of the contractor, the latter has a right to an equitable part of the compensation proportionally to the work done, and reimbursement for proper expenses made. (n)
Source: lawphil.net (RA 386 as amended)