Article 1718
ELI5— what this means for you
The contractor who has undertaken to put only his work or skill, cannot claim any compensation if the work should be destroyed before its delivery, unless there has been delay in receiving it, or if the destruction was...
Official text — RA 386
The contractor who has undertaken to put only his work or skill, cannot claim any compensation if the work should be destroyed before its delivery, unless there has been delay in receiving it, or if the destruction was caused by the poor quality of the material, provided this fact was communicated in due time to the owner. If the material is lost through a fortuitous event, the contract is extinguished. (1590a)
Source: lawphil.net (RA 386 as amended)
Related
RELATED RIGHTS
Legal disclaimer: BatasKo provides general legal information, not legal advice. For advice on contracts, property rights, obligations, or civil damages, consult a licensed Filipino lawyer or the Public Attorney's Office (PAO) at pao.gov.ph.